What we heard, the final plan and construction notificaiton

4 December 2025

Between 18 February to 16 March 2025, we sought your feedback on a draft concept plan for an inclusive playspace at Yeo Park, Ashfield.


Final design

Changes made to the plan include:

  • Play mound, slide and ninja/agility zone relocated due to tree protection zone
  • Additional slide added
  • Additional communal seating for groups to gather and further seating around the parameter was added in response to community feedback
  • Waterplay was enhanced to allow more areas of play.

Construction has begun

Construction commenced on 24 November 2025 and is scheduled to complete in May 2026 (weather permitting).

During this time the playground will be closed.

Any questions?

Contact:

Contact Information
Name Holly Cowdery, Parks Project Manager
Phone 02 9392 5743
Email holly.cowdery@innerwest.nsw.gov.au