Despite some delays due to the COVID lockdowns in Sydney, works have been progressing well along the GreenWay!

Recent developments include:

  • Finalisation of the Review of Environmental Factors report for works in the light rail corridor
  • Tenders are now being sought for the design and construction of works in the light rail corridor
  • Local street upgrade works are largely complete
  • The Dobroyd Point Seawall upgrade is complete
  • Detailed design of the Bay Run upgrade is complete, with construction expected to commence in March 2022
  • Detailed design of the High Voltage feed relocation is complete, with construction expected to commence in March 2022