Feedback reviewed
All feedback will be reviewed and consolidated into an Engagement Outcomes Report. Everyone who provides feedback will be notified when the Engagement Outcomes Report is published.
Council is committed to supporting and encouraging the use of electric vehicles in the Inner West.
Inner West Council has secured funding to roll-out 136 public electric vehicle charging ports across our community over the next 12 months.
There are 95 marked parking spaces proposed. This engagement is to understand the Community’s views on the changing parking controls of these 95 spaces.
The new chargers will range from seven kilowatts to 60 kilowatts and will include pole-mounted and “kiosk” charging stations. They will be installed at kerbside locations throughout the Inner West to help our community transition away from petrol powered cars to electric vehicles.
The provision of public charging is essential in the Inner West as many of our residents do not have off-street parking.
All chargers will be installed by April 2025 and will be open to the public 24 hours a day, seven days a week.
The EV charging stations are fully funded by our partners and NSW Government grants.
In May 2023 Council adopted the Powering Ahead - Inner West Electric Vehicle Encouragement Strategy
In July 2023, Council issued a public charging Expression of Interest (EOI) to determine the various market factors that should be assessed in developing an Inner West EV public charging network.
In September 2023, Council issued an Request for Quote (RFQ) to partner with up to three public charging providers to install kerbside public charging across the Inner West LGA.
In November 2023, Council selected 3 charging providers:
Council supported our three partners in lodging applications for the NSW State Government kerbside charging grants (November 2023) which were awarded in May 2024.
The plan has been developed with consideration of:
Please read the FAQs to find out more information about the chargers including locations, parking restrictions, EV infrastructure and more.
Have questions or want to learn more about this project, contact us below:
Name | Daniela Kiproff |
---|---|
Phone | 02 9392 5321 |
daniela.kiproff@innerwest.nsw.gov.au |
You can provide feedback by:
Other ways to provide feedback
Last day to provide feedback is 11 August 2024.
All feedback will be reviewed and consolidated into an Engagement Outcomes Report. Everyone who provides feedback will be notified when the Engagement Outcomes Report is published.
A report including community feedback will be considered by the Local Traffic Committee on Monday 21 October 2024
Timeline item 1 - complete
Open
This consultation is open for contributions.
Timeline item 2 - active
Under Review
Contributions to this consultation are closed for evaluation and review. The project team will report back on key outcomes.
Timeline item 3 - incomplete
Report to Local Traffic Committee
21 October 2024
The Local Traffic Committee will review Council staff recommendations. A proposal will be reported to the Elected Council.
Timeline item 4 - incomplete
Council decision
5 November 2024
The Councillors will review all information and make a final decision.
Timeline item 5 - incomplete
Instalation
Late 2024 - early 2025
Timeline item 6 - incomplete
Chargers are ready to use
Mid 2025