Camdenville Park upgrade project delays

07 Feb 2020

Update June 2020

In mid 2016 Council was advised that the NSW Roads and Maritime Service (RMS) were compulsorily leasing approximately one third of Camdenville Park for the construction of WestConnex.

As part of the WestConnex project the area originally planned in the Camdenville Park Master Plan for a BMX pump track was taken over and utilised as a construction compound. A small section of the park was permanently acquired to straighten Bedwin Road.

WestConnex project work in this area will continue until the end of 2020. Council has also been advised that further works are required on the Park by Transgrid for the Potts Hill to Alexandria transmission cable project.

Council is working with Transgrid to finalise timelines and minimise disruptions during this project. Works are expected to take approximately 12-18 months to complete.

We are very much committed to implementing the master plan for Camdenville Park, including the much anticipated BMX track.

Once state significant infrastructure works are completed future park improvements including the installation of the BMX Track will be progressed including a design review by Council.


Related projects

Transport for NSW in partnership with Inner West Council are currently planning and delivering a new bridge over the railway at Bedwin Rd, which also forms part of the Westconnex (WCX) M5-St Peters Interchange Active Transport Works, as a condition of the development consent for their project.

We have been successful in gaining funding for the project, through the NSW Government’s St Peters/Alexandria Urban Amenity Improvement Program.

Cycle and pedestrian paths form part of the Westconnex project to improve connectivity and safety and contribute to the active transport network. Council is delivering new and improved pedestrian/cycle paths as part of the M5-St Peters Interchange Active Transport Works funded by Westconnex and Transport for NSW. These include:

  • The Princes Hwy, Canal Rd & Mary St Intersection cycleway
  • The Mary St to Sydenham Station cycleway
  • The Mary St to St Peters Station cycleway includes the construction of the bridge at Bedwin Rd over the railway